Maine PUC Rejects Versant Power's Waiver Request
August 07, 2025
August 07, 2025
WASHINGTON, Aug. 7 -- The Maine Public Utilities Commission, Augusta, has denied a request of Versant Power, Bangor, Maine, to waive a rule concerning small generator interconnections. The order (Docket No. 2025-00112), issued on August 6, 2025, rejects the utility's attempt to apply an additional screening standard to projects seeking to connect to its system. The decision is part of a larger ongoing discussion about grid reliability and the growth of distributed energy resources, particul . . .