Bedford's Community Power Plan Approved by NH Utilities Commission
March 05, 2025
March 05, 2025
CONCORD, New Hampshire, March 5 -- The New Hampshire Public Utilities Commission (PUC) has given the green light to the Town of Bedford's Community Power Electric Aggregation Plan. This decision, detailed in Order No. 28,109, released on March 5, 2025, allows Bedford to proceed with its plan to provide electric power supply and services to its residents, businesses, and other entities.
Bedford submitted its plan for approval on January 9, 2025, in accordance with RSA chapter 53 . . .
Bedford submitted its plan for approval on January 9, 2025, in accordance with RSA chapter 53 . . .