AUGUSTA, Maine, Aug. 15 -- The Maine Public Utilities Commission issued the following order (No. 2024-00074) on Aug. 14, 2024:
* * *
GENERATE NB FUEL CELLS, LLC, Request for Approval of Certification For RPS Eligibility (Curtis Street Fuel Cell Facility)
ORDER
BARTLETT, Chairman; SCULLY and GILBERT, Commissioners
I. SUMMARY
On March 28, 2024, Generate NB Fuel Cells, LLC requested certification of a 20 MW fuel cell faci . . .
* * *
GENERATE NB FUEL CELLS, LLC, Request for Approval of Certification For RPS Eligibility (Curtis Street Fuel Cell Facility)
ORDER
BARTLETT, Chairman; SCULLY and GILBERT, Commissioners
I. SUMMARY
On March 28, 2024, Generate NB Fuel Cells, LLC requested certification of a 20 MW fuel cell faci . . .