PJM Advances to Next Phase of New Interconnection Process
May 21, 2024
VALLEY FORGE, Pennsylvania, May 21 -- PJM Interconnection, a regional transmission organization that coordinates the movement of wholesale electricity, issued the following news release on May 20, 2024:

PJM announced today the completion of Phase I System Impact Studies for 306 proposed generation projects as part of Transition Cycle #1 of PJM's new interconnection process.

Project developers now have 30 days to decide whether to proceed with their new service requests . . .

Targeted News Service Document Request Form

This document is available to you by e-mail if you complete the form below with relevant information. There may be a fee for this article or ongoing service of similar materials. We will be in touch shortly.

Name:
What's your
Affiliation
Government Newspaper / Media Business
Public Policy Individual / Student Educators
Email:
Phone:
Organization, if any:
State/Country you are in:
Additonal questions
or comments:

Click here for more information about our products

Click here for more information about our products