FERC Commissioner Clements Issues Statement on PJM Interconnection
January 19, 2024
January 19, 2024
WASHINGTON, Jan. 19 -- The U.S. Department of Energy's Federal Energy Regulatory Commission issued the following statement by Commissioner Allison Clements on a decision (Docket No. ER24-462-000) involving PJM Interconnection LLC:
* * *
I concur with the Commission's order because I believe that Commission and court precedent dictate that PJM has met its burden under the Federal Power Act. Nevertheless, I write separately to register my concern with the approa . . .
* * *