The Michigan Public Service Commission denied the relief Enbridge Energy LP sought in its request for a declaratory ruling and also rejected the company's request for ex parte approval of plans to relocate the Line 5 pipeline to a tunnel beneath the Straits of Mackinac. The Commission established a full hearing process for the proposal.
Enbridge in Apr . . .
The Michigan Public Service Commission denied the relief Enbridge Energy LP sought in its request for a declaratory ruling and also rejected the company's request for ex parte approval of plans to relocate the Line 5 pipeline to a tunnel beneath the Straits of Mackinac. The Commission established a full hearing process for the proposal.