N.H. PUC Issues Order of Notice Involving Liberty Utilities
CONCORD, New Hampshire, June 6 -- The New Hampshire Public Utilities Commission issued the following order (No. DE 24-066) involving Liberty Utilities (Granite State Electric) Corp.:
* * *
Petition to Amend Tariff
COMMENCEMENT OF ADJUDICATIVE PROCEEDING, NOTICE OF PREHEARING CONFERENCE, AND NOTICE OF HEARING
On April 22, 2024 Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty (Liberty) filed a petition to amend to its tariff to allow it recover costs associated with municipal req
more
N.H. PUC Issues Order of Notice Involving Mill Brook Village Water System
CONCORD, New Hampshire, June 4 -- The New Hampshire Public Utilities Commission issued the following order (No. DW 24-069) involving Mill Brook Village Water System LLC:
* * *
Joint Petition for Approval to Change Ownership of Mill Brook Village Water System, LLC
COMMENCEMENT OF ADJUDICATIVE PROCEEDING AND NOTICE OF PREHEARING CONFERENCE
On May 1, 2024, Mill Brook Village Water System, LLC (Mill Brook) and Marc Liechti and Justin Ahmann (the Buyers) filed a joint petition requesting that the
more
N.H. PUC Issues Order of Notice Involving Town of Loudon
CONCORD, New Hampshire, June 5 -- The New Hampshire Public Utilities Commission issued the following order (No. DE 24-013) involving the Town of Loudon:
* * *
Request for Approval of Loudon Community Power Plan
SUPPLEMENTAL ORDER OF NOTICE
On June 5, 2024, the Town of Loudon (Loudon) filed its revised Community Power Electric Aggregation Plan (the Revised Plan) with the Commission pursuant to RSA 53-E:7 for Commission review and approval. See Procedural Order dated May 9, 2024. RSA 53-E:7, I
more
N.H. PUC Issues Order of Notice Involving Town of Stratford
CONCORD, New Hampshire, June 6 -- The New Hampshire Public Utilities Commission issued the following order (No. DE 24-079) involving the Town of Stratford:
* * *
Request for Approval of Stratford Community Power Plan
ORDER OF NOTICE
On June 5, 2024, the Town of Stratford (Stratford) filed its Community Power Electric Aggregation Plan (the Plan) with the Commission pursuant to RSA 53-E:7 for Commission review and approval. RSA 53-E:7, II provides that
The commission shall approve any plan su
more
N.H. PUC Issues Order of Notice Involving Town of Tamworth
CONCORD, New Hampshire, June 6 -- The New Hampshire Public Utilities Commission issued the following order (No. DE 24-002) involving the Town of Tamworth:
* * *
Request for Approval of Town of Tamworth Community Power Plan
SUPPLEMENTAL ORDER OF NOTICE
On June 5, 2024, the Town of Tamworth (Town or Tamworth) filed its revised Community Power Electric Aggregation Plan (the Revised Plan) with the Commission pursuant to RSA 53-E:7 for Commission review and approval. [See Procedural Order dated M
more
N.H. PUC Issues Order of Notice Involving Unitil Energy Systems
CONCORD, New Hampshire, June 6 -- The New Hampshire Public Utilities Commission issued the following order (No. DE 24-077) involving Unitil Energy Systems Inc.:
* * *
Petition for Approval of Revenue Decoupling Adjustment Factor and Proposed Tariff Changes
COMMENCEMENT OF ADJUDICATIVE PROCEEDING AND NOTICE OF HEARING
On May 24, 2024, Unitil Energy Systems, Inc. (UES or the Company) filed a petition requesting that the Commission approve its proposed revenue decoupling adjustment factors (RDA