Fort McCoy's Brigade Headquarters Construction Project Now 80 Percent Complete as October'23 Begins - Work Remains on Track
October 06, 2023
October 06, 2023
ARLINGTON, Virginia, Oct. 6 -- The U.S. Army Installation Management Command issued the following news release:
As October 2023 began, the construction progress on the $11.96 million transient training brigade headquarters project at Fort McCoy reached past 80 percent complete, according to a recent update from Ken Green with the Army Corps of Engineers Program Office at Fort McCoy.
As recent as early June, the project was at 40 percent complete, and now at early Octobe . . .
As October 2023 began, the construction progress on the $11.96 million transient training brigade headquarters project at Fort McCoy reached past 80 percent complete, according to a recent update from Ken Green with the Army Corps of Engineers Program Office at Fort McCoy.
As recent as early June, the project was at 40 percent complete, and now at early Octobe . . .