Arkansas Nuclear One Returns to Full Service After Successful Refueling
November 21, 2019
November 21, 2019
RUSSELLVILLE, Arkansas, Nov. 21 -- Entergy issued the following news release:
Arkansas Nuclear One's Unit 1 returned to service Wednesday, Nov. 20 at 6:56 p.m. following the completion of its 28th successful refueling and maintenance outage. Control room workers returned the plant to operation, sending electricity to the grid after a planned shutdown that began Oct 5.
"Entergy and the ANO team are committed to providing safe, secure and reliable electricity to the . . .
Arkansas Nuclear One's Unit 1 returned to service Wednesday, Nov. 20 at 6:56 p.m. following the completion of its 28th successful refueling and maintenance outage. Control room workers returned the plant to operation, sending electricity to the grid after a planned shutdown that began Oct 5.
"Entergy and the ANO team are committed to providing safe, secure and reliable electricity to the . . .