ALBANY, New York, Oct. 7 -- The New York State Public Service Commission issued the following ruling (Case No. 18-T-0499) involving NextEra Energy Transmission New York:
Application of NextEra Energy Transmission New York, Inc. for a Certificate of Environmental Compatibility and Public Need Pursuant to Article VII of the Public Service Law for the Construction of a 20 Mile 345 Kilovolt Transmission Line Located in the Town of Royalton, Niagara County, and the Towns of Alden, Newste . . .
Application of NextEra Energy Transmission New York, Inc. for a Certificate of Environmental Compatibility and Public Need Pursuant to Article VII of the Public Service Law for the Construction of a 20 Mile 345 Kilovolt Transmission Line Located in the Town of Royalton, Niagara County, and the Towns of Alden, Newste . . .