Con Edison has completed a $200 million construction project that will increase electric service reliability in several neighborhoods on the east side of Staten Island.

The two new 138,000-volt, underground cables - also called feeders - run 4.6 miles across the island, from a substation in Travis on the west side to a substation on Dongan Hi . . .

Targeted News Service Document Request Form

This document is available to you by e-mail if you complete the form below with relevant information. There may be a fee for this article or ongoing service of similar materials. We will be in touch shortly.

Name:
What's your
Affiliation
Government Newspaper / Media Business
Public Policy Individual / Student Educators
Email:
Phone:
Organization, if any:
State/Country you are in:
Additonal questions
or comments:

Click here for more information about our products

Click here for more information about our products