FERC ISSUES ORDER TO ISO NEW ENGLAND ACCEPTING, SUSPENDING LARGE GENERATOR INTERCONNECTION AGREEMENT, ESTABLISHING HEARING, SETTLEMENT JUDGE PROCEDURES
October 06, 2008
WASHINGTON, Oct. 6 -- The U.S. Department of Energy's Federal Energy Regulatory Commission issued the following order:

Before Commissioners:

Joseph T. Kelliher, Chairman;
Suedeen G. Kelly, Marc Spitzer,
Philip D. Moeller, and Jon Wellinghoff.

ISO New England Inc.

ER08-950-000
ER08-950-001

ORDER ACCEPTING AND SUSPENDING LARGE GENERATOR INTERCONNECTION AGREEMENT AND ESTABLISHING HEARING AND SETTLEMENT J . . .

Targeted News Service Document Request Form

This document is available to you by e-mail if you complete the form below with relevant information. There may be a fee for this article or ongoing service of similar materials. We will be in touch shortly.

Name:
What's your
Affiliation
Government Newspaper / Media Business
Public Policy Individual / Student Educators
Email:
Phone:
Organization, if any:
State/Country you are in:
Additonal questions
or comments:

Click here for more information about our products

Click here for more information about our products